Powertech Technology Inc.
Hsinchu Science Park – Plant 3- Industry Semiconductor Manufacturing Industry
- Case location No. 15, Datong Road, Hukou Township, Hsinchu County, Taiwan
Project Overview:
MEP Engineering
Project Duration:
2018.09.28 - 2020.12.31
Contract Systems:
■Electromechanical Engineering
■HVAC Engineering
■Fire Protection Engineering
Project Overview:
Cleanroom Engineering for 1st & 2nd Floors
Project Duration:
2020.10.06 - 2020.12.31
Contract Systems:
■Electrical System Automation Engineering
■HVAC Engineering
■Cleanroom Decoration Engineering
■Process Piping Engineering
■Central Monitoring Engineering
■Fire Protection Engineering
■Aspirating Smoke Detection System
Project Overview:
8th Floor Clean Room Project
Project Duration:
2022.01.24 ~ 2022.06.03
Contract Systems:
■Electrical Engineering
■Fire Protection Engineering
■HVAC Engineering
■Process Engineering